PJM Interconnection
PJM Interconnection LLC (PJM) is a regional transmission organization (RTO) in the United States. It is part of the Eastern Interconnection grid operating an electric transmission system serving all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Oh
Signal Radar
Five-axis snapshot of this entity's footprint
Mentions × Lab Attention
Weekly mentions (solid) and average article relevance (dotted)
Timeline
8- PolicyJun 4, 2026
PJM warns of AI data center load growth from 5 GW to 25 GW by 2035, citing grid reliability and cost risks
View source- current load:
- 5 GW
- projected load 2035:
- 25 GW
- interconnection queue delay:
- 4 years
- capacity price increase:
- 15%
- PolicyMay 13, 2026
PJM data reveals AI data centers face 3-4 year post-approval delays, exceeding queue wait times
View source - PolicyMay 13, 2026
PJM overhauled interconnection processes as AI datacenter projects now average over 7 years to go live, with post-approval delays of 4 years.
View source- average project time:
- 7+ years
- post-approval delay:
- 4 years
- preliminary applications:
- 220 GW
- peak demand forecast 2036:
- 210 GW
- Regulatory ActionMay 12, 2026
$22 billion in total PJM transmission project costs over 3 years
View source - Regulatory ActionMay 12, 2026
FERC complaint filed by Maryland OPC challenging PJM cost allocation rules for AI data centers
View source- complaint amount:
- $2 billion
- Product LaunchMay 1, 2026
PJM launched reformed interconnection process using agentic AI from Tapestry, receiving 811 projects totaling 220GW
View source- projects:
- 811
- capacity gw:
- 220
- Regulatory ActionApr 3, 2026
PJM reported 220GW interconnection queue for AI data centers
View source- queue capacity gw:
- 220
- affected region:
- Eastern Interconnection, US
- PolicyJan 1, 2026
PJM electricity prices spiked 76% in 2026 due to AI data center demand
View source- price increase percentage:
- 76%
Relationships
5Partnered
Sued
Frequently appears with
3Entities that show up in the same articles — shared coverage, not a stated relationship.
Recent Articles
4Google-Backed Tapestry Claims 811 Grid Apps Processed in Under an Hour
~Google-backed Tapestry processed 811 PJM interconnection applications in under an hour, claiming to slash a months-long process to minutes.
78 relevanceOpenAI Eyes 10GW Ohio Data Center with Nvidia Backing
~OpenAI is negotiating a 10GW Ohio data center with Nvidia backing, potentially costing $500B on federal land.
100 relevancePJM Warns AI Data Center Load Could Break Power Market Assumptions
-PJM warns AI data center load could grow 5x to 25 GW by 2035, colliding with queue delays and outdated market rules. Regulators flag reliability and c
90 relevancePJM Power Prices Spike 76% as Fed Watchdog Demands Tech Giants Pay for
~PJM electricity prices spiked 76% from AI data center demand. Federal watchdog demands tech giants pay for grid upgrades, as local bans multiply.
100 relevance
Predictions
No predictions linked to this entity.
AI Discoveries
No AI agent discoveries for this entity.
Sentiment History
| Week | Avg Sentiment | Mentions |
|---|---|---|
| 2026-W18 | 0.00 | 2 |
| 2026-W20 | -0.20 | 4 |
| 2026-W23 | -0.30 | 1 |
| 2026-W24 | 0.05 | 2 |