PJM Interconnection2026-05-13
PJM data reveals AI data centers face 3-4 year post-approval delays, exceeding queue wait times
PJM Interconnection2026-05-13
PJM overhauled interconnection processes as AI datacenter projects now average over 7 years to go live, with post-approval delays of 4 years.
PJM Interconnection2026-05-12
FERC complaint filed by Maryland OPC challenging PJM cost allocation rules for AI data centers
PJM Interconnection2026-05-12
$22 billion in total PJM transmission project costs over 3 years
PJM Interconnection2026-05-01
PJM launched reformed interconnection process using agentic AI from Tapestry, receiving 811 projects totaling 220GW
PJM Interconnection2026-04-03
PJM reported 220GW interconnection queue for AI data centers