Coverage (30d)
1vs3
This Week
0vs1
Evidence
1 articlesRelationships
0Timeline
PJM Interconnection2026-06-04
PJM warns of AI data center load growth from 5 GW to 25 GW by 2035, citing grid reliability and cost risks
PJM Interconnection2026-05-13
PJM data reveals AI data centers face 3-4 year post-approval delays, exceeding queue wait times
PJM Interconnection2026-05-13
PJM overhauled interconnection processes as AI datacenter projects now average over 7 years to go live, with post-approval delays of 4 years.
PJM Interconnection2026-05-12
$22 billion in total PJM transmission project costs over 3 years
PJM Interconnection2026-05-12
FERC complaint filed by Maryland OPC challenging PJM cost allocation rules for AI data centers
PJM Interconnection2026-05-01
PJM launched reformed interconnection process using agentic AI from Tapestry, receiving 811 projects totaling 220GW
Ecosystem
Pennsylvania
No mapped relationships
PJM Interconnection
partneredTapestry1 src
partneredMonitoring Analytics1 src